USACE schedule specification UFGS 01 32 01.00 10 — the complete checklist, paragraph by paragraph

3 November 2026

On a Corps of Engineers construction contract, the project schedule is governed by one section of the specifications: UFGS 01 32 01.00 10, Project Schedule. It sets what the schedule must contain, how it must be built in Primavera P6, how it is coded for the Corps' Resident Management System (RMS), and how it is updated each month. It also says what happens when it is not followed, in paragraph 3.2.3:

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial, or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

There is no official checklist for this section. The Whole Building Design Guide publishes review checklists for the Navy's scheduling section, and none for the Corps'. So we built one: every requirement in the current edition, with the paragraph it comes from, listed in the order you would check a file.

A Corps of Engineers project engineer in a hard hat and safety vest watches a concrete paving machine
A Corps of Engineers project engineer checks concrete placement on an Army project in Powidz, Poland, in 2022. Photo: U.S. Army, Christopher Gardner, public domain, via Wikimedia Commons.

Which edition this covers

This checklist follows the edition of UFGS 01 32 01.00 10 dated August 2026, which superseded the February 2023 edition. Unified Facilities Guide Specifications are revised several times a year, and a contract is governed by the edition bound into it, not the newest one. Check the date on the section in your contract before relying on any paragraph number below.

The banner at the top of every UFGS section names USACE, NAVFAC and AFCEC together. The Preparing Activity line beneath it says whose section this is: the Corps'. The Navy's own scheduling section is UFGS 01 32 17.00 20, a different document with different requirements.

What the section covers

72 requirements · 15 parts of the section · every one with its paragraph

Requirements of UFGS 01 32 01.00 10 by part of the sectionSoftware versionSoftware version: 11PaymentPayment: 11Cost loadingCost loading: 77Activity durationsActivity durations: 55Schedule contentSchedule content: 55SDEF activity codesSDEF activity codes: 1515ConstraintsConstraints: 66MilestonesMilestones: 11CalendarsCalendars: 33Logic and relationshipsLogic and relationships: 55Scheduling settingsScheduling settings: 11Progress and updatesProgress and updates: 66SubmittalsSubmittals: 44Primavera P6 settings (3.12)Primavera P6 settings (3.12): 1010QC reports and RMSQC reports and RMS: 22
Every requirement in the checklist below, by the part of the section it comes from. Read from the rules profile when this page was built.

Two groups are almost entirely mechanical: the SDEF activity codes in paragraph 3.3.7 and the Primavera P6 settings in paragraph 3.12. Each is a code, a value or a setting. Both are settled in P6 before the file is exported, and both are easy to get wrong when a schedule is copied from another job. The rest asks for judgement as well as data, from durations and logic to cost loading and the updates.

The checklist

ParagraphRequirement
Software version
2.1.2.1P6 export version not newer than the Government's
Payment
3.2.3Withholding and payment rejection exposure
Cost loading
3.2Cost loading balances to the contract line items
3.2.1No negative cost loading
3.2.1No front-end loading
3.2.2Submittal activities carry no cost
3.3.20Punch list correction cost-loaded at 1 percent minimum
3.3.20.1As-built drawings cost loading floor
3.3.20.2O&M manuals cost loading floor
Activity durations
3.3.15Original duration changes require approval
3.3.19Remaining duration of unstarted activities
3.3.2Activity duration ceiling
3.3.2Activity calendar-day span
3.3.2 / 3.3.10Curing and acceptance periods
Schedule content
3.3.3Design and permit activities present
3.3.4Procurement activities present
3.3.5Mandatory activities present
3.3.6Government activities shown
3.4.2The sequence of activities is reasonable and realistic
SDEF activity codes
3.3.7SDEF coding dictionary present
3.3.7 / ER 1-1-11 App ASDEF export viability
3.3.7 / ER 1-1-11 App AUnit Cost Record viability
3.3.7.1Workers Per Day (WRKP) assigned
3.3.7.2Responsible Party (RESP) assigned
3.3.7.3Area of Work (AREA) assigned
3.3.7.4Modification Number (MODF) usage
3.3.7.5Bid Item (BIDI / CLIN) assigned
3.3.7.5Every BIDI value is a CLIN that exists in the contract
3.3.7.6Phase of Work (PHAS) assigned
3.3.7.7Category of Work (CATW) assigned
3.3.7.8Feature of Work (FOW) assigned
ER 1-1-11 App A, ACTV note (2)Activity ID must be numeric, max 10 digits
ER 1-1-11 App A, ACTV note (3)Activity description maximum 30 characters
ER 1-1-11 App A, ACTV note (6)Only ES and LF constraints survive SDEF export
Constraints
3.3.8Artificial float constraints prohibited
3.3.8Mandatory constraints that override logic prohibited
3.3.8No unauthorised constrained dates
3.3.8.1Project start not earlier than NTP
3.3.8.1NTP Acknowledged start milestone with Start On constraint
3.3.8.2End Project finish milestone and float behaviour
Milestones
3.3.8.3 / 3.3.8.3.1 / 3.3.8.3.2Phase milestones and interim completion dates
Calendars
3.3.10Calendars developed and assigned appropriately
3.3.10Working days, weekends and holidays
3.3.9Adverse weather accounted for
Logic and relationships
3.3.11Only two open-ended activities
3.3.11Required relationship types on every activity
3.3.16Leads (negative lags) prohibited
3.3.16Start-to-Finish relationships prohibited
3.3.16Lags not used to absorb or create float
Scheduling settings
3.3.17Retained logic required, progress override prohibited
Progress and updates
3.3.12Default progress data disallowed
3.3.12Actual dates rewritten between updates
3.3.13Out-of-sequence progress
3.3.14Activities added, deleted, or renamed without approval
3.3.18Percent complete reflects earned value
3.9.1Artificially improving progress
Submittals
3.3.21Early completion schedule must be fully resource loaded
3.4.1Preliminary schedule scope and cost balance
3.4.2Initial schedule submitted on time and covering the full contract
3.5.1File identifies its schedule type, contract number and data date
Primavera P6 settings (3.12)
3.12.aActivity codes defined at project level
3.12.bCalendars defined at project level
3.12.cActivity duration type is Fixed Duration and Units
3.12.dPercent complete type is Physical
3.12.eCalendar work hours per day is 8.0
3.12.fCritical activities defined by Longest Path
3.12.hCost loading through one lump-sum non-labor resource
3.12.iActivity IDs do not exceed 10 characters
3.12.jActivity names have a verb-noun structure
3.12.kAll work calendars end the day at the same hour
QC reports and RMS
3.3.12Actual dates must match the Daily QC Reports
QCS Manual 2.38 / Prime ContractorPrime contractor responsibility code is PRIM

Download the checklist as a spreadsheet (CSV)

The download carries one row per requirement, with the paragraph, the requirement and the sentence from the specification it rests on. It opens in Excel.

The settings to check in P6 before you export

Paragraph 3.12 is a list of Primavera P6 settings, and it is the quickest part of the section to get right because each item is a single value. Among them:

ParagraphThe setting the section requires
3.12.c"Activity Duration Types must be set to "Fixed Duration & Units"."
3.12.d"Percent Complete Types must be set to "Physical"."
3.12.eTime period preferences at the default "8.0 hr/day, 40 hr/week, 172 hr/month, 2000 hr/year", and calendar work hours per day at 8.0
3.12.f"Set Schedule Option for defining Critical Activities to "Longest Path"."
3.12.i"Activity ID's must not exceed 10 characters."

Paragraph 2.1.2.1 adds one more that is easy to miss: export the .xer "in a version of P6 no newer than that used by the Government." A file saved from a newer P6 than the Government's will not open on their side, however good the schedule is.

A Corps of Engineers engineering technician explains a quality assurance inspection to contractors on site
A Corps of Engineers construction quality management seminar for contractors, near Kandahar, Afghanistan, in 2011. The Corps' quality control reports are where the actual dates in a schedule update are checked. Photo: Karla Marshall, U.S. Army Corps of Engineers, public domain, via Wikimedia Commons.

Two requirements the file cannot prove

Some requirements can only be checked against documents outside the schedule. Two matter more than the rest.

Actual dates must match the daily QC reports. Paragraph 3.3.12: "Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule." No tool can check this from the .xer. Reconcile the actual dates with your QC reports before each update.

Cost loading must balance to the contract line items. Paragraph 3.2 ties the schedule's cost to the contract's line items (CLINs). The schedule file holds what you distributed across activities, not what the contract is worth, so the balance can only be checked with the contract value in hand.

What is changing in fiscal year 2027

Two changes affect how a Corps schedule reaches the Government.

RMS is being replaced. The guide specification for the Resident Management System, UFGS 01 45 00.15 10 (Change 1, August 2026), carries this note: "During FY 2027, RMS will be transitioning to the Construction Management Platform (CMP). Districts will be transitioned in phases." Fiscal year 2027 began on 1 October 2026. Until a district has moved, its projects must include both the RMS section and the new CMP section, 01 45 00.25 10.

SDEF is no longer the only way in. RMS has accepted P6 XML imports since patch 444 (October 2023) and lists XER in the same import screen since patch 588 (January 2026). The SDEF activity code structure in 3.3.7 is still mandatory: "This exact structure is mandatory." What may change is which problems in the file only matter on the SDEF route. We cover the routes in SDEF, P6 XML or XER.

Frequently asked questions

What is UFGS 01 32 01.00 10?

The Project Schedule section of the Unified Facilities Guide Specifications, prepared by the U.S. Army Corps of Engineers. It sets the requirements for the contractor's CPM schedule on a Corps construction contract: content, P6 settings, SDEF activity codes, cost loading, updates and submittals.

How long can an activity be in a USACE schedule?

Paragraph 3.3.2 limits non-procurement activities to an original duration of 20 workdays or 30 calendar days. Procurement activities, as paragraph 3.3.4 defines them, are not covered by that limit.

Can USACE withhold payment for the schedule?

Yes. Paragraph 3.2.3 says that failure to meet the section may result in disapproval of the schedule and rejection of payment requests until compliance is met, and that the Contracting Officer may withhold 10 percent of the pay request amount until directed revisions are made.

Does the Navy use the same scheduling section?

No. The joint banner on every UFGS section names USACE, NAVFAC and AFCEC, but NAVFAC's scheduling section is UFGS 01 32 17.00 20, a separate document with its own requirements.

Is there an official USACE schedule review checklist?

Not for UFGS 01 32 01.00 10. The Whole Building Design Guide publishes baseline and monthly update review checklists for the Navy's section 01 32 17.00 20. The checklist on this page is derived from the Corps' section itself, paragraph by paragraph.

Photographs from the U.S. Army Corps of Engineers are public domain. Their use here does not imply endorsement by the U.S. Army, the Corps of Engineers or the Department of Defense, and Structuraline is not affiliated with any of them.

Sources

  • Unified Facilities Guide Specifications, UFGS 01 32 01.00 10 Project Schedule, August 2026 edition — Whole Building Design Guide.
  • UFGS 01 45 00.15 10 Resident Management System (RMS), November 2023, Change 1 August 2026 — the note on the transition to CMP.
  • USACE ER 1-1-11, Appendix A — the Standard Data Exchange Format (SDEF).
  • Whole Building Design Guide, review checklists published for UFGS 01 32 17.00 20 (NAVFAC).

This checklist is an automated reading of published specification text, not a review of your contract. The section bound into your contract, and any amendment to it, governs.